Newport Bay / San Diego Creek Watershed Project Study Plan April 1999
Subaccount
Task
Cost $
01
Public Involvement
$67,900
02
Institutional Studies
$19,400
03
Social Studies
$3,300
04
Cultural Resources
$27,000
05
Environmental Studies
$256,000
06
Fish & Wildlife Studies
$50,700
07
Economic Studies
$87,000
08
Survey and Mapping
$321,900
09
Hydrology and Hydraulics
$478,000
10
Geotechnical Investigations
$46,000
11
Design and Cost Estimates
$33,800
12
Real Estate Studies
$22,400
13
Study Management
$313,100
14
Plan Formulation
$54,800
15
Report Preparation
$81,300
16
Programs and Project Management
$85,400
17
Review Support
$57,900
22
$30,600
18
Contingencies (10%)
$204,000
SUBTOTAL
$2,240,500
23
"Spin-off" PSP Costs
$100,000
TOTAL STUDY COSTS
$2,340,500
Upper Newport Bay / San Diego Creek Watershed Planning Initiative
Newport Bay / San Diego Creek Watershed Project Study Plan
Ecosystem Restoration Feasiblity Study
Ecosystem Restoration Feasiblity Study Appendices